PROJECT UPDATES
Master's Transportation Headquarters + Production Facility – PHASED OCCUPANCY
Client: Master’s Transportation
Project Size: $70 million | 320,000 SF
Project Partners: Miller Stauch Construction | Finkle + Williams Architecture | Renaissance Infrastructure Consulting | Port KC
As construction progresses, occupancy approvals from the city will be obtained in phases. The service portion of the building is currently in use, equipped with four post lifts, tire changers, tire balancers, paint booth, and air compressors. The next phase of occupancy for the service building offices is scheduled for April 11th. The production building is on track to be substantially completed by late April, with the client's move-in planned for late May.
The exterior cladding system for the office building is currently under installation, while interior finishes have commenced.
Substantial completion for the offices is targeted for June 9th, with a phased client move starting in mid-June and continuing through early July.
Photos Courtesy of Miller Stauch Construction
Roy Blunt Health Science Innovation Center – CONSTRUCTION
Client: Missouri Southern State University
Project Size: $48M | 68,000 SF
Project Partners: Crossland Construction | CGA Architects | RDG | Pulse Design
Steel and concrete work is nearly complete and expected to wrap up shortly. Interior CMU (Concrete Masonry Unit) work is scheduled to finish by the end of the month, providing a solid foundation for the next phases. Plumbing, HVAC, fire protection, and electrical rough-in work is currently ongoing on the first floor, along with important interior framing activities.
Meanwhile, exterior framing has commenced on the west facade, with sheathing and air barrier installation planned to follow closely behind. Exterior masonry work is set to begin in April, adding to the structure’s durability and aesthetic.
A topping-out ceremony took place on March 14, with the final beam being set on April 1, marking a significant milestone in the project’s progression.
Basehor-Linwood High School Addition – CONSTRUCTION
Client: Basehor-Linwood USD 458
Project Size: $60M | Bond 2024
Project Partners: McCownGordon Construction | HTK Architects | Schlagel & Associates
Construction for the Basehor-Linwood Bond 2024 kicked off with a groundbreaking ceremony for the high school addition on January 13. After some winter weather-related delays, mass excavation, grading, and installation of underground utilities are currently in progress on-site!
Evergy has successfully removed the existing power lines and has provided a new energy feed to the school. Additionally, WaterOne has installed a new water main and meter to get ready for upcoming sewer work. Site preparations are nearing completion for the sewer line installation that will extend westward.
Vibratory stone columns are being installed to support the building pad, with site beams and footings scheduled for construction once all stone columns are completed. New sidewalks and access paths are also being constructed near the football field.
Pittsburg Regional Crime Center + Laboratory – DESIGN DEVELOPMENT
Client: Kansas Bureau of Investigation | Pittsburg State University
Project Size: $56M | 62,000 SF
Project Partners: McCownGordon Construction | PGAV Architects | Henderson
The design development process is actively underway. An early work package is being planned to facilitate construction commencement in September. We anticipate having a full set of construction documents ready by late September.
The project’s completion is targeted for December 2026.
Salina Healthcare Clinic + Educational Training Center – SCHEMATIC DESIGN
Client: Salina Health Education Foundation
Project Size: $44M | 88,000 SF
Project Partners: McCownGordon Construction | HFG Architecture
We are currently working with McCownGordon and their trade partners on MEP (mechanical, electrical, plumbing) design opportunities and strategies for the Salina Healthcare Clinic + Educational Training Center project.
Schematic design documents are scheduled to be completed later this month, with a budget ready mid-May. Design development documents will be completed and reviewed by the owner by the end of August, and construction documents will be completed by late November. A final GMP will be presented to the owner after the start of the new year.
Canyon Creek Apartment Homes – CONSTRUCTION
Client: MRE Capital
Project Size: $46 million | 5 buildings | 212 units
Project Partners: Schlagel | Streamline General Contractors | KTI | TranSystems
Foundations are now complete for all five buildings. Site utility work is currently underway. The installation of curbs and gutters, as well as parking lot paving, is scheduled for April. In addition, wood frame construction is expected to begin in late April.
The targeted completion date for the first building is January 2026, with the overall project anticipated to be completed by May 2026.
INDUSTRY INSIGHTS
$474M Bond Approved for KCPS
Kansas City Public Schools is ready to embark on their first bond-funded district-wide improvements since since 1967 after voters in Kansas City approved the $474M bond this past Tuesday. 85% of voters voted in favor of the bond.
Eskie + Associates is will be serving as Owner’s Representative to the nine charter school partners through their building upgrades on behalf of KCPS.
For more information visit the KCPS bond website.
Eskie is MOVING (Down the Street)!
After several wonderful years and many memories at the 12114 office, our growing team has called for a new home base.
Eskie + Associates will move to 12260 State Line Rd, Leawood, KS in this coming June. After some tenant improvements to make it our own, we expect to occupy the new space on June 10!
UPCOMING EVENTS
Breakthrough T1D Dream Gala 2025
When: Saturday, May 3, 2025 | Starts at 5:30 PM
Where: Muehlebach Tower of the Kansas City Marriott Downtown, Kansas City, MO
What: The Dream Gala is a fundraising event for community and corporate leaders in the type 1 diabetes (T1D) community benefiting the Breakthrough T1D Kansas & Missouri chapter. Type 1 diabetes is an autoimmune disorder that affects over 1.7 million individuals in the United States alone. This event includes a seated dinner, exquisite silent auction, exciting live auction, and inspiring Fund A Cure.
About the Organization: Breakthrough T1D leads the way to more effective solutions by connecting the brightest minds to advance treatments, influence policy, and improve access to care.
DBIA NextGen Executive Round Table Event
When: May 21, 2025 | 4:30–6:30 PM
Where: Burns & McDonnell
SAVE THE DATE — Eskie’s Owner + Managing Partner, Erin Eskie Merrill, is excited to be a participant in the upcoming DBIA event. Stay tuned for more details and to learn where you can register.
USA-Kansas Uniting Leaders Conference
When: Wednesday, May 29 – Friday, May 31, 2025
Where: Wichita, KS – Hyatt Regency and Century II Performing Arts & Convention Center
We are excited to attend our second USA Kansas Uniting Leaders Conference! Day one of the event will have a vendor showcase at the convention center, so stop by to chat with the Eskie + Associates team anytime from 4:00 - 7:00 PM on May 29th. We are eager to connect with everyone and share our success stories in education, as well as our partnership with USA Kansas! Stay tuned for our booth number and location.
Head For the Cure 5k
When: Sunday, August 24, 2025
Where: Corporate Woods Building 40
SAVE THE DATE — Join us in August for the annual Head for the Cure 5k, an event that raises awareness of glioblastoma and funds for research into fighting the disease. Register or donate today at the link below.
ESKIE TEAM SPOTLIGHT
This year, Eskie + Associates’ Founder Dennis Eskie celebrated his 81st birthday. With a birthday landing on St. Patrick’s Day, it calls for twice the celebration in the Eskie Family.
Every year, the Eskie’s celebrate Dennis with a family trip over the holiday. This year was no exception.
Having been able to travel to Indian Wells, California, the Eskie’s were excited as always to adhere to their annual traditions; dressing in festive attire, making Dennis’ mom’s famous chocolate sheet cake, and partaking in a family dance party.
This year was extra special, with Dennis’ sister and her family also in attendance.
Thank you for reviewing our quarterly update! We are proud of our team and the projects we support in Kansas City. If you need help building your project team, creating a project plan, managing owner responsibilities, and reducing risks, contact Eskie + Associates. Our expert Owner's Reps can guide your project from start to finish while you focus on your daily operations.